Latest PRINCE2-Foundation Pass Guaranteed Exam Dumps with Accurate & Updated Questions
PRINCE2-Foundation Exam Brain Dumps - Study Notes and Theory
The PRINCE2 Foundation exam covers the basic principles of PRINCE2 methodology, including the seven principles, seven themes, and seven processes. It also covers the roles and responsibilities of the project management team, as well as the techniques and tools used in the PRINCE2 methodology. The exam is a multiple-choice test that is conducted online, and candidates are required to pass the exam in order to obtain the PRINCE2 Foundation certification. The certification is recognized globally and is highly valued by employers in various industries.
The EXIN PR2F certification exam is an ideal certification for individuals looking to gain knowledge and understanding of the PRINCE2 methodology. The exam covers a wide range of topics, and successful completion of the certification exam is recognized globally. EXIN is a trusted and reliable provider of certification exams and training courses, making it an ideal partner for professionals looking to enhance their skills and knowledge in the field of project management.
NEW QUESTION # 129
Which theme verifies that a project's products are fit for purpose?
- A. Quality
- B. Progress
- C. Organization
- D. Business case
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality
NEW QUESTION # 130
Which is a purpose of the Risk theme?
- A. Establish mechanisms to control any unacceptable deviations from plan
- B. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
- C. Establish mechanisms to manage risks at the corporate or programme level of an organization
- D. Establish a cost-effective procedure to identify, assess and control uncertainty
Answer: D
NEW QUESTION # 131
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
- A. Stage Plan
- B. Benefits Review Plan
- C. Team Plan
- D. Project Plan
Answer: A
NEW QUESTION # 132
What is used to identify any organization or interested party who needs to be informed of project closure?
- A. Project Brief
- B. Communication Management Strategy
- C. Configuration Management Strategy
- D. Project management team structure
Answer: B
NEW QUESTION # 133
Which statement about project roles is CORRECT?
- A. Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled
- B. The project team structure defined in PRINCE2 must be used, but other roles may be added
- C. The project organization must be defined using the roles and responsibilities in PRINCE2
- D. The project board roles defined in PRINCE2 must be used, but other roles can be defined as required
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 134
Which enables the project's products and all interdependencies to be clearly identified and documented?
- A. Product-based planning technique
- B. Product breakdown structure
- C. Quality review technique
- D. Quality Management Strategy
Answer: A
NEW QUESTION # 135
As a minimum requirement for applying the risk theme, what must specifically be assessed?
- A. Whether a risk may cause the project to exceed its cost tolerance
- B. Whether a risk may impact the underlying technical assumptions
- C. Whether a risk may alter the project's business justification
- D. Whether a risk may affect the project-level quality tolerances
Answer: C
NEW QUESTION # 136
Which is the purpose of the Change theme?
- A. Identify, assess and control any potential and approved changes to baselined products
- B. Prevent change to baselined products
- C. Assess and control uncertainty
- D. Establish mechanisms to monitor and compare actual achievements against those planned
Answer: A
NEW QUESTION # 137
Which is an objective of the quality review technique?
- A. To define the quality methods required within a project
- B. To provide a common understanding of what products a project will create
- C. To determine the quality responsibilities of a project team
- D. To baseline a product
Answer: D
NEW QUESTION # 138
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. has responsibility
- B. decides who is responsible
- C. and the project board are responsible
- D. and the team manager(s) are accountable
Answer: A
Explanation:
Reference http://prince2.wiki/Directing_a_Project
NEW QUESTION # 139
Which does the Executive need to ensure is in place before the project is initiated?
- A. The Project Plan has been approved
- B. An understanding of how the project will contribute to corporate objectives
- C. The Project Initiation Documentation is complete
- D. All Work Packages are authorized
Answer: B
NEW QUESTION # 140
Who should act as the communication channel between a project and corporate or programme management?
- A. Project Assurance
- B. Project Board
- C. Project Support
- D. Project Manager
Answer: B
NEW QUESTION # 141
Which is an objective of the Directing a Project process?
- A. Create and authorize the project mandate
- B. Control the day-to-day running of the project
- C. Provide accurate progress information to the Project Manager
- D. Provide management control and direction
Answer: D
Explanation:
Section: Volume A
NEW QUESTION # 142
Which is a minimum requirement for applying the quality theme?
- A. To define quality criteria in product descriptions
- B. To provide administrative support for quality controls
- C. To appoint external reviewers for quality reviews
- D. To define the project's approach to quality assurance
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 143
Which of the following are true statements about a Project Brief?
1 . Used to provide a foundation for the Initiating a Project process
2 . Created in the Starting up a Project process
3 . Used by the Project Board to make an assessment of a project's progress
4 . Used as the basis of the Project Initiation Documentation
- A. 1, 3, 4
- B. 1, 2, 4
- C. 1, 2, 3
- D. 2, 3, 4
Answer: B
NEW QUESTION # 144
Which is a purpose of a quality register?
- A. To issue a unique reference number for each product
- B. To identify corrective actions that are required after an audit by quality assurance
- C. To record the quality management approach for a product
- D. To detail the number and type of quality activities to be conducted
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality#The_Quality_Register
NEW QUESTION # 145
Which is an objective of the 'directing a project' process?
- A. To tailor the project's products and roles so that the project suits the circumstances
- B. To provide an interface between the project and corporate management
- C. To ensure the stage products are delivered to the stated quality standards
- D. To respond to the project mandate by starting up a project
Answer: B
NEW QUESTION # 146
Which is an objective of the 'initiating a project' process?
- A. To ensure that user acceptance of the products is confirmed
- B. To ensure that the business case is kept under review
- C. To ensure that the planned products are delivered within tolerances
- D. To ensure that baselines are established and controlled
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Initiating_a_Project#Objective
NEW QUESTION # 147
What process provides the information required to decide whether to authorize the delivery of a project?
- A. Starting up a Project
- B. Initiating a Project
- C. Directing a Project
- D. Managing Product Delivery
Answer: B
NEW QUESTION # 148
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
- A. Project Brief is assembled and approved
- B. project approach appropriate for delivering a project is selected
- C. aim is to establish sound foundations to achieve a successful project
- D. minimum necessaryis done to decide if a project is worthwhile
Answer: C
NEW QUESTION # 149
When should the Project Board refer to corporate or programme management for a decision?
- A. The Senior Supplier or Senior User needs to be changed
- B. It is forecast that project level tolerance will be exceeded
- C. Any request for change needs to be approved
- D. The stage requires resources
Answer: B
Explanation:
Section: Volume A
NEW QUESTION # 150
Which is a purpose of quality planning?
- A. Produce the Project Plan with resource and schedule information
- B. Document approval records for those project products that have met their quality criteria
- C. Define the structure of the project management team
- D. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
Answer: D
NEW QUESTION # 151
......